sub_logo.gif - 3022 Bytes
sub_products_title.gif - 2229 Bytes
sub_top_contact.gif - 2317 Bytessub_top_search.gif - 984 Bytessub_top_map.gif - 1061 Bytessub_top_home.gif - 771 Bytes
sub_nav_left.gif - 167 Bytes  
sub_industies.gif - 4958 Bytes
sub_biotech.gif - 2168 Bytes
sub_pharma.gif - 2211 Bytes
sub_specialty.gif - 2450 Bytes
sub_goods.gif - 2236 Bytes
sub_line.gif - 219 Bytes
sub_purification.gif - 2258 Bytes
sub_wastewater.gif - 2451 Bytes
sub_mineral.gif - 1312 Bytes
sub_pulp.gif - 2311 Bytes
sub_micro.gif - 2164 Bytes
sub_airpolution.gif - 2404 Bytes
sub_competencies.gif - 3014 Bytes
sub_process.gif - 2408 Bytes
sub_costanalysis.gif - 2028 Bytes
sub_scheduling.gif - 2602 Bytes
sub_debottle.gif - 2207 Bytes
sub_cycle.gif - 2540 Bytes

sub_line.gif - 219 Bytes
sub_impact.gif - 2496 Bytes
sub_treatment.gif - 2490 Bytes
sub_purification.gif - 2295 Bytes
sub_emissions.gif - 1829 Bytes
sub_airpolution.gif - 2406 Bytes
sub_bottom.gif - 9461 Bytes
SchedulePro® sub_about_collage.gif - 9824 Bytes
collage_fade.gif - 338 Bytes collage_bg.gif - 45 Bytes

 


Read more about the latest version.

SchedulePro Basics

A SchedulePro project consists of recipes and resources.

Recipes describe a series of processing steps or tasks to be executed. Recipes provide information about how the steps relate to one another in time and about the resources required. SchedulePro provides an easy-to-use interface for creating and editing recipes.

Resources include equipment, work areas, labor, materials, utilities and inventory capacity. SchedulePro has a convenient calendar interface for entering time-based resource availability including:

  • Equipment down-time and maintenance schedules
  • Labor shift schedules
  • Material shipments and receipts

SchedulePro Organization

Recipes and Resources

A schedule consists of a series of recipes with specific timing and resource assignments. Each execution of a recipe in SchedulePro is a batch.
 

Scheduling Approaches

SchedulePro provides a number of options for generating a schedule:

  • Schedule forward from a start date: The user decides which recipes to run; SchedulePro does the rest.
  • Schedule backward from a due date: The user decides which recipes to run; SchedulePro does the rest.
  • Manual scheduling: The user sets timing and/or resources; SchedulePro reports any resource conflicts.
  • Schedule editing: The user may add or delete batches in an existing schedule. The user may also change durations or resource assignments for specific processing steps. SchedulePro optionally makes any necessary adjustments to avoid resource conflicts.
     

Schedule Visualization

SchedulePro displays schedules in a variety of formats:

  • An explorer tree view (similar to recipes and resources)
  • As an interactive Gantt chart
  • As a resource occupancy chart – this view shows the blocking of equipment or work areas over time.

Gantt Chart

Gantt Chart – color coded by recipe hierarchy (campaign – batch – procedure)

Equipment Occupancy Chart

Occupancy chart for equipment – color coded by batch
 

Schedule Analysis

SchedulePro generates the following charts:

  • Resources (material, labor or utilities demand, or waste generation) as a function of time
  • Material inventories as a function of time.
  • Equipment utilization statistics

Resource Demand Chart

Material Demand Rate over Time

Inventory Chart

Inventory of a Waste Holding Tank (emptied daily)
 

Data Export

SchedulePro generates a variety of tables and reports (including the data for all the charts). All the tables and reports are saved in HTML format which may be posted on a website or read by many popular spreadsheet or word processing programs.
 

SuperPro Designer Compatibility

SchedulePro can import processes from SuperPro Designer. Each process in SuperPro becomes a recipe in SchedulePro.
 

Compatibility with Other Programs

SchedulePro can export schedules in the MS Project® database format. This format is compatible with Project 2000 and Project 2002.